Turbine in place

The Archimedes Screw turbine is now in place – it arrived last week with some very precise crane work! Installation work is now underway with a target commissioning date of 20th April

Archimedes Screw arrives on site

We’ve arrived at the most exciting part of the project with the Archimedes Screw now on site and awaiting installation shortly

Many thanks to Marches Biogas who have held the Archimedes screw assembly on their yard until ready to go to site. Some people have asked about the cladding on the screw channel – it will go on after the screw is in place; the river has been to high to complete these works over the winter. See the plans for an idea of how it will look when complete